This morning marks the beginning of day eleven -- just two weeks from starting with nothing. The exterior walls are more than halfway to the top and continuing to rise rapidly.

The current construction slump in southwest Florida has enabled the contractor to find workers available immediately. We'll be discussing some minor changes in roof structure with the project manager later today. So far the construction has caused only minor inconveniences to our staff, and, other than the satellite dish incident during week one, no technical problems.

Sod has already been placed around the edge of our new expanded parking area.

Our workers are taking it up to the next level.